Project Highlights
Naval Weapons Facility
USN Colts Neck, New Jersey
• Dredged to depths of 41 feet MLW
• A dredge volume of 60,000 cubic yards of contaminated
sediment adjacent to active deep water piers required working
24 hours a day to meet the 60 day completion schedule
• Rigorous environmental controls due to endangered fish
habitat
• Exposure to northeast winds presented difficult dredging
conditions
•Equipment included the Wood 1, Eddie Carroll, and Joe
Verrochi
|