New Bedford Harbor Dredge Phase II
New Bedford , Massachusetts


Project Dates: 2005

Owner:
City of New Bedford-Harbor Development Commission

Project Engineers/Managers:
Apex Environmental, Inc.



 


 
Jay Cashman’s Wood 1 Bucket Dredge
 

Project Highlights

New Bedford Harbor Dredge / Capping
New Bedford, Massachusetts

Wood 1 Dredge removed the top of the proposed new CAD cell #1 using a “CableArm” environmental clamshell-style bucket

• Removed material was loaded into split hull dump scows for disposal into the Borrow Pit

After removing the top of the CAD, 85,000 CY of sand was dredged, completing the CAD cell construction

Excavated material was successfully used for the EPA’s pilot PCB Underwater Capping Project in the New Bedford Harbor

All work performed met or exceeded the environmental constraints specific to this project


 