Wetlands Sediment Remediation Project
Wayland, Massachusetts
• Excavated over 5,000 CY of PCB impacted wetland
sediments
•Sediments were dewatered in-situ and, after excavation,
were processed through a pug mill
•Amended as necessary with a cement mixture for
offsite transport to a hazardous disposal facility
• Cashman used land mats to create a temporary roadway,
aqua dams to serve as temporary flood mitigation
measures, and erosion control measures to ensure
compliance with erosion sediment control requirements
• Excavated areas were backfilled, with manufactured
wetland soil/sediment, to pre-excavation topography
• Wetlands were restored via seeding and replanting
specified mixtures and plants
• Wetlands were restored via seeding and replanting
specified mixtures and plants
|