Building cities, communities and infrastructures that last…

Throughout our history, Jay Cashman, Inc. has worked quietly behind the scenes—and often under them—building the vital infrastructure, foundations and civil engineering networks essential to business communities along the East Coast. We’ve performed some of the most challenging and complex subsurface construction projects ever undertaken. From caissons, sheet piling, H-pile, pipe pile, concrete pile, and slurry walls to soil mixing/stabilization to depths of up to 130 feet, Cashman is the below-grade contractor of choice in the Northeast.

Our civil engineering expertise has contributed to the construction of many of the nation’s major new highways, tunnels, bridges and commuter railroad lines. Even on the most challenging projects, our experienced engineers and expert personnel have worked in conjunction with some of the country’s preeminent engineering professionals to design/construct site-specific solutions. And, Cashman’s proficiency in earth retention systems, deep soil mixing and stabilization, pile driving and complex foundations has been instrumental in the construction of numerous new buildings, office towers, power plants and more throughout the area.

Cashman developed and executed an innovative solution that allowed for the completion of Boston’s Deer Island Wastewater Treatment Plant effluent outfall tunnel. In what the Boston Globe called “an unprecedented engineering feat,” Cashman positioned a jack-up barge in 120 feet of water to ventilate the 9.25 mile tunnel 950 feet below the water-line with fresh air - allowing construction workers to remove safety plugs from diffusers.

On Boston’s Central Artery Tunnel Project (CA/T), a Cashman-led joint venture adapted deep soil mixing technologies to meet the challenges of the Fort Point Channel, a vital link along the CA/T’s critical path. Cashman/PKA created a block of earth with the density and compressive strength to accommodate the three tunneling methods (cut and cover, tunnel jacking ad immersed tube) used to complete the link between the Mass Pike and the Ted Williams Tunnel, which leads to Logan Airport.

The company’s single largest contract to date (as a joint venture sponsor) is the CA/T contract to construct 1,800 feet of the Artery from Chardon Street to the Charles River, where eight lanes (four northbound and four southbound) emerge from below grade at the Fleet Center and under Causeway Street to meet the 10-lane, cable stay bridge that crosses the Charles River. Extensive underpinning of 19 bents was required to support 1,400 feet of the elevated artery while work progressed safely below grade. Major utility relocations, temporary facilities and service connections played important roles in clearing the path for the cut-and-cover tunneling operation.





Heavy Civil Portfolio

 

 
Heavy Civil Portfolio:


 



  Roadways
Millbury Interchange
MBTA South Station Ramp
I - 495 Interchange

Bridges
Menauhant Bridge
Brightman Street Bridge
Washington Bridge

Tunnels
Chardon Street to Charles River
Porter Street Outfall
Fort Point Channel Soil Stabilization
Fore River Siphon Directional Drilling
Railwork
Greenbush Commuter Rail

Slurry Walls
Chardon Street to Charles River
Manulife
Fort Point Channel Soil Stabilization

Soil Mixing
Fort Point Channel Soil Stabilization

Site Work

Spectacle Island

Wharf District Parks

North Point Park


Demolition
Fort Dawes Demolition
Deer Island- Prison Demo/Excavation
Long Island Piers

Foundations
Boston Convention Center
Manulife Financial Corp. US Operations Headquarters
Distrigas High Pressure Gas Facility
New England Aquarium IMAX Theater

Pile Installation
Distrigas High Pressure Gas Facility
Bucksport Energy Piling Contract
Sithe Energy

Buried Utility Work
Chardon Street to Charles River
Greenbush Commuter Rail
Deer Island - Earthwork, Landfill, Roadway

Jet Grouting
Fort Point Channel Marine Work
Chardon Street to Charles River

 

Copyright© 2005, Jay Cashman Inc., All rights reserved.