Project Date: 3/99-5/99
Owner:
Parsons Energy and Chemicals Group, Inc.
|
"The
Contract required driving a significant number of pipe piles
in a very short time schedule with a substantial liquidated
damages penalty; we finished it on budget and ahead of schedule."
--John Malm, Jay Cashman, Inc.
|
 |
 |
|
| |
Excavation and piling work was the critical first step in the fast-track construction of the Bucksport Energy Facility
|
| |
Project
Highlights
Bucksport Energy Piling Contract
Bucksport, Maine
• Driving over 325 14-inch pipe piles
in less than five weeks.
• Time critical first step in fast track construction of Bucksport
Energy Facility
• Hauled and disposed of contaminated soils at low cost to owner.
• Worked closely with Owner's
representative to calculate and order pile quantities
to successfully avoid time delays.
|
|