Bucksport Energy Piling Contract
Bucksport, Maine


Project Date: 3/99-5/99

Owner:
Parsons Energy and Chemicals Group, Inc.


"The Contract required driving a significant number of pipe piles in a very short time schedule with a substantial liquidated damages penalty; we finished it on budget and ahead of schedule."

--John Malm, Jay Cashman, Inc.






 

Excavation and piling work was the critical first step in the fast-track construction of the Bucksport Energy Facility

  Project Highlights

Bucksport Energy Piling Contract
Bucksport, Maine

• Driving over 325 14-inch pipe piles in less than five weeks.

• Time critical first step in fast track construction of Bucksport
Energy Facility

• Hauled and disposed of contaminated soils at low cost to owner.

• Worked closely with Owner's representative to calculate and order pile quantities to successfully avoid time delays.



Copyright© 2005, Jay Cashman, Inc., All rights reserved.

Website Designed by Modern Creative