Fort Point Channel Marine Work
Boston
, Massachusetts


Project Date: 6/02-3/03

Owner:
Massachusetts Highway Department, Central Artery Tunnel

Project Engineers/Managers:

McGuire Associates

"This was a complicated little piece of work: we had to excavate contaminated sediments from the bottom of a tidal, free flowing channel to precise dimensions and then cover the entire cross section with pre-cast concrete erosion control mats and riprap. Most of the time we couldn't see what we were doing: we couldn't have done it without skilled surveyors and divers"

- Carl T. Gustenhoven, Project Manager, Jay Cashman, Inc
.

 


  Project Highlights

Fort Point Channel Marine Work
Boston, Massachusetts

• This project required excavation and over-land transportation of 9,300 CY of very wet, contaminated sediments from the upper reaches of Boston’s Fort Point Channel. All of this was accomplished without a single spill or violation of extremely stringent odor control requirements.

• Cashman divers and surveyors installed and grouted 6,800 SY of pre-cast concrete erosion control mats, under water, with little or no visibility to achieve an exact final channel cross section. Final hydrographic examination showed that Cashman’s team had “hit the mark” and the client was extremely pleased with the final product.

• Cashman equipment managers modified existing marine excavation equipment to meet the project requirements for “environmental dredging” that mitigated the amount of turbidity and sediment agitated by dredging operations.

• Existing marine and land equipment had to be specially modified to perform a water operation that, due to low bridges, could not be accessed from open water!

• Cashman divers worked under extremely cold water and air temperatures and challenging currents without incident and at maximum efficiency.



Copyright© 2005, Jay Cashman, Inc., All rights reserved.

Website Designed by Modern Creative