| |
Project
Highlights
Greenbush Commuter Rail
Weymouth, Massachusetts
This project is being completed by the MBTA on a design-build
basis, and includes the Design-Build Contractor's obligation
to furnish a complete design of the project, to construct
the project as designed and to otherwise comply with all
the requirements of the Design-Build Contract. The MBTA
provided a conceptual design (approximately 15%) of the
project to firms interested in participating in the project.
In March 2002 the MBTA Board of Directors authorized the
selection of a Joint Venture of Jay Cashman, Inc. and Beatty
Balfour, Inc. (CBB) Construction Co., to design and construct
this project. CBB was one of four Design-Build Contractors
pre-qualified to submit bids to complete the work proposed
under this contract. Notice to proceed for design was
issued in early April of 2002 with Notice to proceed for
construction to be granted beginning at specific sites
in the fall of 2002. Construction was completed on the
primary field office for the Greenbush project in early
June 2002 for CBB and MBTA staff working on the project.
The office is located at 1580 Commercial Street in East
Weymouth, the future sight of East Weymouth Station.
This project will restore commuter
rail service on the existing right-of-way known as the
Greenbush corridor through the towns of Braintree, Weymouth,
Hingham, Cohasset and Scituate, Massachusetts. The project
begins at the connection with the existing MBTA Old
Colony Main Line at the Braintree Wye in East Braintree,
and extends 18 miles easterly along the former New Haven
Railroad Greenbush Branch to the terminus in the Greenbush
section of Scituate. The project involves the reconstruction
of existing, largely out-of-service railroad right-of-way
as a single track railroad with four controlled passing
sidings of approximately 1 mile in length each. Once
completed, the facility will be equipped with a new
signal and communications system and end-of-the-line
train layover facility. In addition, certain freight
facilities in Braintree will be relocated off-line.
The right-of-way is currently active
for local freight service on the first 1.5 miles in
East Braintree. The remainder of the right-of-way is
either out of service or abandoned. The proposed commuter
rail service will provide twelve (12) round trips between
Boston-South Station and Greenbush each weekday and
eight (8) round trips on weekends. Scheduled peak-direction
one-way trip time between South Station and Greenbush,
including a stop at Quincy Center, will be 59 minutes.
Seven new commuter rail stations will
be constructed along the right-of-way, each with an
800-foot long high-level platform. New commuter parking
lots at the stations ranging in size from 200 to 1000
spaces each will provide a total of approximately 3000
spaces corridor wide. Stations will be similar to those
constructed on the other Old Colony lines and will include
accommodations for bicycle parking and passenger drop-off/pick-up
by automobile, van, or bus.
Nine existing single span railroad
bridges will be reconstructed with new ballast deck
superstructures and new or rehabilitated abutments and
wing walls. Work will be performed on two existing roadway
bridges over the right-of-way: one (1) bridge will be
replaced in its entirety and the other will be repaired.
Four (4) new grade separations will be constructed:
at Weymouth Landing (shallow cut tunnel); Green Street
(new railroad bridge over lowered roadway); Hingham
Square (underpass with 800 foot long cut and cover tunnel
crossing under three (3) roadways); and Rocky Lane (new
highway bridge on new roadway alignment crossing over
the right-of-way).
Of the forty-three (43) existing roadway
grade crossings on the right-of-way, ten (10) will be
closed and eight (8) eliminated by grade separations.
The remaining twenty-five (25) crossings, plus one (1)
new roadway crossing and three (3) pedestrian crossings,
will be reconstructed with new grade crossing warning
systems and supplemental safety measures in accordance
with the Swift Act. The entire facility will be designated
as a quiet zone (no routine use of train whistles at
crossings). Intersection improvements will be made at
locations immediately adjacent to the railroad and station
entrances and at seven (7) remote locations. At one
(1) location on Route 3A in Scituate, an existing signalized
intersection will be replaced with a combination of
traffic signals and a roundabout. New or modified traffic
signals will be installed at a total of nineteen (19)
locations.
The project includes extensive mitigation
measures to address noise, vibration, historic, wetland,
and other impacts. Noise barriers will be constructed
at six (6) locations, vibration-dampening ballast mats
will be installed under a total of 3.5 miles of track,
and screen plantings will be installed along 6 miles
of right of sidelines. Fencing, consisting of chain
link, security, black chain link, solid wood, or steel
picket, depending on location, will be provided along
virtually the entire length of the right-of-way. Mitigation
agreements have been reached with all five (5) Towns
detailing specific mitigation items to be provided.
In accordance with the Section 106 Agreement Resource
Consultations, a Project Conservator will monitor the
project to ensure that historic properties are protected
and mitigated as agreed. An Independent Observer will
monitor the Project to ensure that wetlands are protected
and mitigated in accordance with certain environmental
approvals. Additional mitigation measures, such as noise
abatement of individual homes, will be performed by
the MBTA directly.
|