New Pier and Bulkhead on Deer Island, Boston Harbor, including Concrete Work, Pier Construction, Dredging and Pile Driving.

 

Project Highlights

Deer Island Marine Facilities
Deer Island, Massachusetts

• Drove 1,200 16-inch diameter pipe piles ranging from 75’ to135’.

• Constructed a 640 linear foot tied back bulkhead.

• Processed dewatered dredged material into road gravel.

• Constructed a heavy duty roll-on/roll-off pier 400’x490’.

• Constructed transfer bridges and a personnel shuttle float.

• Utilized 10,000 cubic yards of micro-silica concrete.

• Constructed a 640’ long relieving platform/pier facility.

• Constructed on-site concrete batch plant.