Effluent Outfall Diffusers
Boston, Massachusetts


Project Date:

Owner:
Massachusetts Water
Resources Authority


Designer:
Project Engineers/Managers
ICF Kaiser Engineers


"There was a high spirit of cooperation between the Contractor, the Designers, the Owner, the Subcontractors and Construction Managers"

--David A. Beck -ICF Kaiser Engineers, Area Manager

 

 

A dredge barge, jack-up drilling barge with a Manitowoc 4100 ringer crane, diving vessel, grouting barge and other marine support vessels, performed complex offshore installation work.

 

Project Highlights

Effluent Outfall Diffusers
Boston, Massachusetts


Off-site fabrication of sea bed concrete diffusers.

Installation of 55 diffusers on risers extending 250 feet below the ocean bottom.

Working nine miles offshore with jack-up barge and complex marine and drilling equipment.

Installation work was performed in water depths of 120 feet.

Precision drilling to guarantee a riser's ís position at tunnel depth.




Copyright© 2005, Jay Cashman, Inc., All rights reserved.

Website Designed by Modern Creative