Hull Revetment Improvements
Hull, Massachusetts


Project Date: 10/99-5/00

Owner:
Massachusetts Department of Environmental Management

Project Engineers/Managers:
Massachusetts DEM




"As always scheduling the construction activities during difficult winter conditions is a challenge.”

-Mike Bissonette, Project Manager




 

 

The key objective was to complete the work during the winter season and restore the site during the spring.

 

Project Highlights

Hull Revetment Improvements
Hull, Massachusetts

• Placed over 11,000 cubic yards of stone on the exposed Massachusetts shore.

• Work completed during winter conditions with a 5 month schedule.

• Complete site restoration and improvements performed.

• Materials were trucked to the site with sequential placement of stone and material deliveries to maximize productivity.

 