Tampa Harbor Maintenance Dredging, Hillsborough County, Florida

VIDEO

IMAGES

DETAILS

Client: USACE Jacksonville District
Value: $8,100,000
Project Date: November, 2015 - May, 2016
Project Cut-sheet: Download

SUMMARY

As part of a hopper dredging IDIQ MATOC with the USACE Jacksonville District, Cashman Dredging used the trailing suction hopper dredge Atchafalaya to conduct 43-ft and 34-ft dredging. The project scope included dike maintenance, weirs, bird monitoring, marine animal observation, and turbidity monitoring.

Dredging began in fall 2015 along the length of the Tampa Bay Federal Navigation Channel encompassing the entire Tampa Bay from Mullet Key Channel Lighted Buoy 26 west of the Sunshine Skyway Bridge, extending the entire length of the Tampa Bay Channel. The goal was to remove shoaled material from the Federal Channel and consisted of maintenance dredging of Cuts A through F of Tampa Bay Channel; Cuts J, J2 and K within the Port Tampa turning basin; and Gadsden Point Cut of Hillsborough Bay.

PROJECT HIGHLIGHTS

  • Cashman's split-hull trailing suction hopper dredge Atchafalaya was responsible for removing shoaled material from the federal channel 7 days a week, 24 hours a day, supported by various other vessels.
  • Removed material was transported to a booster barge in Hillsborough Bay. The booster barge was secured with spuds outside of the navigable channel along the south side of Disposal Island 3.
  • Dredged material was dewatered and then pumped to and placed in DMMA Site 3-D.
  • Approximately 1,500 linear feet of floating and submerged pipeline was placed in line with the booster barge to the shoreline. The pipeline was marked with lighted buoys, for local traffic.
  • A total of 361,749 cubic yards of material was removed.
  • Work included turbidity monitoring, sea turtle trawl sweeping and relocation (hoppers), and endangered species observers, as well as operation and maintenance of DMMA Site 3-D at the direction of the Contracting Officer.
  • Cashman received an overall rating of "Exceptional" based on excellent performance and the highest ratings assigned to two rating elements considered to be of very high importance: Quality and Management. Cashman was commended for our exceptional efforts and dedication to meet the USACE's requirements of completing the project on time, on budget, and providing a high-quality project result with no accidents or environmental incidents.

Link to see the article announcement on Dredging Today.com