2017 America’s Cup 'Cross Island' Land Reclamation, Bermuda

IMAGES

DETAILS

Client: West End Development Corp. (WEDCo)
Value: $21.2 million
Project Date: August 2015 - December 2016
Project Cut-sheet: Download

SUMMARY

CASHMAN was selected as the primary contractor responsible for land reclamation efforts for this high-profile project—the largest undertaken in Bermuda since WWII. CASHMAN was part of the team that completed the first-phase construction of “Cross Island,” which was the home of the Event Village for the 2017 America’s Cup, hosted by Bermuda. The new land provided a viewing area for the races in nearby Great Sound, and the Event Village hosted activities associated with the sailing tournament including team bases, a pit row, food and beverage venues, entertainment, and concerts. 

Bermuda-based construction company BCM McAlpine was the overall project manager, with ACBDA Ltd. as Owner’s agent. The dredging and land preparation began in October 2015 and was completed in January 2016. At that time, CASHMAN began the marine construction aspects of the project, to install the splash wall and sheet piling on the perimeter, and complete the preparation of the site. Planners started installing utilities by late summer 2016.

CASHMAN proposed an innovative Design-Build (D-B) option at the bid stage, providing nearly $5.0 million in savings to owner West End Development Corporation (WEDCo). Through value engineering and ongoing dialogue between the WEDCo and project teams, constant evolution of the D-B works led to the most efficient, cost-effective, and environmentally sound installation for this $21.2 million project in the South Basin of the Royal Naval Dockyard. 

The first part of the project involved relocating and re-handling approximately 140,000 cubic yards of sand onto a shallow plateau to begin the creation of the land. CASHMAN relocated the sand within the site to create the landfill, using the clamshell dredge Dale Pyatt, and dozers to create the site. Innovative soil vibro-compaction methods were utilized on the re-handled material to provide deep compaction of the fill, thereby reducing future settlement. Another 166,000 cubic yards of crushed granite were transported in seven shiploads by the bulk carrier MV Balder from Canada and offloaded via conveyor belt in the landfill area. CASHMAN relocated the granite within the site using loaders and dozers.

With bulkhead wall and pile cap design provided by PND Engineers of Seattle, WA, the contract also included:

  • Construction of a cast-in-place 1,250-linear foot cantilevered retaining ‘splash wall’ on the south and east of the site as storm protection;
  • Installation of 1,350 linear feet of sheet piling in an open cell pattern on the north and west; 
  • Construction of 1,350 feet of reinforced concrete pilecap on top of the new sheet pile bulkhead; 
  • Extension of multiple utilities into the newly reclaimed land; 
  • Construction of bridge approaches; 
  • Final site grading.

CASHMAN utilized its own East Coast resources to man the US-flagged dredge Dale Pyatt and to ensure the project schedule was met. Besides the Dale Pyatt, CASHMAN transported a sheet-piledriving crane and hammers, and earth-moving and compacting equipment to the site. The project employed over 25 local subcontractors and suppliers throughout all phases of construction. All reclamation and marine construction work was performed in proximity and without damage to the Royal Naval Dockyard, a listed building of historic significance. 

The first phase of construction of Cross Island was completed in August 2016. 
The project attracted avid local attention and was reported on in detail by the local newspaper, The Royal Gazette.

The project was featured in the June 2016 Issue of International Dredging Review Magazine.

Back